Asbury Creek Intake Replacement Projects
This is a State mandated project to improve Asbury Creek conditions in order to encourage fish passage. Click here for the State's Project Description. Tentative Completion Date: Fall 2027.
District must move, 200 feet upstream, the point at which we take water from Asbury Creek. Once that is done, the State will remove/ replace the culvert under highway 101 with a bridge. District will then replace/ reroute current in-ground water main with one that is attached to the undercarriage of the bridge.
Project Description Project Plan